Airline Catering Facility Refurbishment
UK
The client needed to adapt a large legacy airline catering facility of approximately 16,800 sqm to accommodate a substantially different process requirement whilst the existing facility remained operational.
The focus for the design involved the analysis of the changing requirements of the process, and where departments appeared to be under-utilised or inefficient from a layout perspective.
The design optimisation was constantly cross-checked from an operational perspective, resulting in an evolutionary defragmentation process which consolidated and condensed the operation, thus releasing more capacity.
One of the most complex areas was the Hot Kitchen, where the whole kitchen was completely upgraded with a significant increase in capacity and efficiency.
The refurbishment involved a carefully choreographed sequence of 36 simultaneous live projects whist the facility itself remained operational.